CONDURIL's works in Malawi

Label150

Construction of water supply schemes in Lilongwe District

Assignment Construction of water supply schemes in Lilongwe District
Localization Lilongwe - Malawi
Main characteristics Construction of a water collection and treatment area, including administrative buildings, main pipeline and distribution network in PVC with diameters between 25 and 200 mm, construction of 3 water tanks (200 m3, 150 m3 and 100 m3), new water points in Nathenje, Kasyia and Nsaru, in Lilongwe District.

Main pipeline: 11 km
Distribution network: 36 km
Start/Finish 02-2013 / 08-2013
Participation 100%
Client Ministry of Water Development and Irrigation of th
Label184

Upgraded Kamuzu Barrage

Assignment Upgraded Kamuzu Barrage
Localization Liwonde - Malawi
Main characteristics The project involves the rehabilitation of the Kamuzu Dam in the Shire River, including the construction of a new bridge immediately downstream of the dam, with a length of 140 m over 14 spans.
For carrying out the work it will needed the execution of two cofferdams, the first on the left bank to allow the implementation of the first works stage, including 6 spans, and then another cofferdam on the right bank for the execution of works adjacent to the remaining 8 spans.
Major quantities of the project:
Earthworks: 30,000 m
Cofferdam: 55,000 m
Concrete: 13,000 m
Sheet Piles: 11,000 m
Start/Finish 01-10-2014 / 15-10-2017
Participation 100%
Client Government of Malawi - Ministry of Agriculture, Ir