CONDURIL's works in Senegal

Label149

HIGHT DELTA ADDUCTORS–LOT1

Assignment HIGHT DELTA ADDUCTORS–LOT1
Localization SENEGAL
Main characteristics Works of rehabilitation and construction of reinforced concrete of hydraulic structures:

-Gravity taken of 8 passages at Ronkh;

-New complementary dam of Boundoum;

-New gated bridge-culvert of Boundoum;

- New gated bridge-culvert of Diawel;

-New gated bridge-culvert of Diambar;

-New gated bridge-culvert of Demba;

-New adit structure G
Start/Finish 21-01-2013 / 20-11-2014
Participation 100%
Client MCA-SENEGAL
Label167

DELTA ADDUCTORS–LOT2

Assignment DELTA ADDUCTORS–LOT2
Localization SENEGAL
Main characteristics EARTHWORKS AND REINFORCED CONCRETE CONSTRUCTION WORK ON THE FEEDER PIPES IN THE DELTA – LOT 2:

Rehabilitation of feeder pipes:
_ Gorom upstream: stripping and treating, clearance and dykes on 24 800 m;
_ Gorom downstream: Raising the dykes between project G and Krankaye dam on 7 800 m;
_ Kassack North: stripping and treating, clearance and dykes on 10 300 m between the Diambar project and Ndiael siphon;
_ Kassack South: dykes on 9 730 m between the Ndiael siphon and the Demba project; stripping and treating, clearance
_ Lampsar upstream: stripping and treating, clearance and dykes on 20 110 m between the Boundoum bridge gates and the Ross-Béthio regulation project;
_ Lampsar middle: Raising the dykes between Ross Béthio bridge and Ndiol bridge on 24 930 m;
_ Lampsar downstream: stripping and treating, clearance (on a stretch located at 602 m) and dykes on 17 310 m between the Ndiol project and Mboubéne bridge;
_ Krankaye Canal: dyke containment, placing a 25-cm laterite bearing layer on both banks: length of canal – 8 670 m;
_ Ngalam: stripping, treating and dykes on 12 900 m;
_ Gandiolais Canal, recalibration of the canal on 7 900 m.
Construction and rehabilitation of hydraulic projects
_ Rehabilitation of Mboubéne bridge through replacement of two gates and reinforcement of protection;
_ Equipping Ndaiwdoune bridge with seven wall gates and wooden gates.
_ Dam work, two channels with gates on the Gandiolais canal;
_ Monitoring work on three no. 1 deltas with 2 channels with gates
_ Monitoring work on the three no. 2 tributaries with 2 channels with gates
_ Connection work on the Gandiolais canal, 3 frames with double channels;
Start/Finish 2013 / 2015
Participation 100&
Client MCA-SENEGAL